Huntington Middle School: The Next Chapter

The proud history of Huntington High School and Huntington Middle School will continue with the construction of a new 600-student middle school, anticipated to open during the second semester of the 2025-2026 school year.

The new middle school is part of the city’s Southeast Community Resource Area that is set to include a public library and community center, as well as sports and recreation features.

1 / 9
2 / 9
3 / 9
4 / 9
5 / 9
6 / 9
7 / 9
8 / 9
9 / 9

Huntington Middle School (Image: Quinn Evans)
Huntington Middle School (Image: Quinn Evans)
Huntington Middle School (Image: Quinn Evans)
Interior Hall (Image: Quinn Evans)
Interior (Image: Quinn Evans)
Library (Image: Quinn Evans)
Gymnasium (Image: Quinn Evans)
Exterior of Gymnasium (Image: Quinn Evans)
Site plan for the Southeast Community Resource Area (Image: Quinn Evans)

Construction Progress Update

April 24, 2025

The Huntington Middle School building site is divided into four (4) building zones, A, B, C, and D. MEB General Contractors, Inc, the Contractor, is developing the building pad in the order of zones C, D, B, and A. The work completed in these building zones are as follows:

Building Zones

In Zone "C" the contractor has completed the following:

  • Finish installation of load bearing masonry walls in the corridors.
  • Waiting on structural steel. First structural steel anticipated to arrive mid-April '25.

In Zone "D" of the building the contractor has completed the following:

  • Plumbing rough-ins under-slab for the kitchen and cafeteria are complete.
  • Electrical rough-ins under-slab for the kitchen and cafeteria are complete.
  • Start prep work for the structural slab on grade for the kitchen and cafeteria.
  • Plumbing rough-ins under slab complete for the classrooms.
  • Contractor is currently roughing-in branch circuits in the classrooms.
  • Load bearing masonry walls 75% complete for the classrooms.

In Zone "B" of the building the contractor has completed the following:

  • Plumbing rough-ins under-slab for classrooms is approximately 75% complete.
  • Electrical rough-ins under slab for classrooms is approximately 75% complete.
  • Load bearing masonry walls are approximately 20% complete for classrooms.
  • Administration area concrete slab is on grade and complete.
  • Begin prep for structural slab in classrooms.

In Zone "A" of the building the contractor has completed the following:

  • Auditorium concrete slab is on grade and complete.
  • Auditorium stage is formed and sub-floor currently being prepped for concrete.
  • Plumbing rough-ins under-slab for the band room and chorus room are complete.
  • Electrical rough-ins under-slab for the band room and chorus room are complete.
  • Remaining Plumbing and Electrical rough-ins under slab in classrooms are approximately 25% complete.
  • Begin to prep for the structural slab on the main corridor, space A1002.

Field House

  • Below grade insulated foundations are complete.
  • Plumbing rough-ins under grade are approximately 10% complete.
  • Electrical rough-ins under grade are approximately 10% complete.
  • Load bearing masonry walls are approximately 20% complete.

Construction photo
Admin Area

Construction photo
Area A, Corridor A1022

Construction photo
Area B Classrooms

Construction photo
Area B, Corridor B1075

Construction photo
Area D, 1st and 2nd Floor Classrooms

Construction photo
Area D, 1st and 2nd Floor Classrooms

Construction photo
Area D, Corridor D1083

Construction photo
Auditorium

Construction photo
Band Room

Construction photo
Cafeteria

Construction photo
Chorus Room

Construction photo
Main Corridor A1002

Huntington Construction Project

Construction Progress Update

Architect: Quinn Evans

Contractor: MEB General Contractors

Projected Timeline:

  • March 1, 2024
    Advertise Project

  • April 12, 2024
    Bid Opening

  • May 20, 2024
    Notice of Intent to Award

  • August 22, 2024
    Building Permit for Construction

  • September 5, 2024
    Groundbreaking Ceremony, 9 a.m.

  • February 3, 2026
    Substantial Completion

  • April 5, 2026
    School Site and Building Completion

  • June 4, 2026
    Final Completion